Topic
Queenstown transport business cases since 2017
New Zealand transport projects funded through NZTA follow a staged business case process. A programme business case sets out the problem and the mix of responses. Indicative and detailed business cases then test the options and make the investment case for specific packages. A single-stage business case combines these steps for smaller projects.
Since 2017 Queenstown has had business cases at each stage:
- Programme business cases: the Queenstown Integrated Transport Programme Business Case (QTS-006), the Town Centre Masterplan programme (QTS-011) and the Te Kirikiri Frankton programme (QTS-026).
- Indicative business cases: town centre parking (QTS-008), public and passenger transport facilities (QTS-010), and the 2024 Queenstown Public Transport Business Case (QTS-095).
- Single-stage business case: the Wakatipu Active Travel Network (QTS-023).
- Detailed business case: the 2020 Queenstown Business Case (QTS-062, summary QTS-050), with its appendices.
This page lists every business case, chapter and appendix held in the archive, so the options assessments, economic cases and costings can be read in the original documents.
Key records
39 records
- Queenstown Public Transport Business CaseQTS-0952024
- Queenstown Public Transport Business CaseQTS-0942024
- Queenstown Public Transport Business CaseQTS-0932024
- Queenstown Transport Business Case – AppendicesQTS-0642020
- Queenstown Business CaseQTS-0622020
- Wakatipu Basin Future Public Transport DemandQTS-0612020
- Queenstown Business Case – Commercial CaseQTS-0562020
- Queenstown Business Case – Management CaseQTS-0572020
- Queenstown Business Case – Preferred OptionQTS-0582020
- Queenstown Business Case – Strategic ContextQTS-0592020
- Preferred programme sequencing reportQTS-0602020
- Appendix C14 Land Requirement PlansQTS-0522020
- Queenstown Business Case – Summary ReportQTS-0502020
- Appendix F Commercial Case - F1 Risk RegisterQTS-0492020
- Appendix A Strategic CaseQTS-0442020
- Appendix B Options AssessmentQTS-0452020
- Appendix C15 Environmental and SocialQTS-0462020
- Appendix E Financial Case - Appendix E1 FundingQTS-0472020
- Appendix G Management CaseQTS-0482020
- Appendix D Economic CaseQTS-0422020
- Appendix B27 Technical Note 42: SH6A Bus SignalQTS-0412020
- Appendix B14 Technical Note 38: SH6 Frankton EastQTS-0402020
- Frankton Design ReportQTS-0392020
- Appendix B19 Technical Note 25: VURT AnalysisQTS-0372020
- Appendix C8 Safety in Design RegisterQTS-0352020
- Appendix C11 Technical Note 36: IntelligentQTS-0342020
- Appendix B8 Technical Note 42: SH6A Bus SignalQTS-0312020
- Appendix B16 Technical Note 24: ArterialsQTS-0302020
- Appendix C10 Technical Note 22: Travel DemandQTS-0292020
- Appendix B23 Technical Note 19: Scope ExtensionQTS-0282020
- Te Kirikiri Frankton Integrated TransportQTS-0262019
- Wakatipu Active Travel Network Single StageQTS-0232019
- Queenstown Integrated Transport Programme BusinessQTS-0122018
- Queenstown Public and Passenger TransportQTS-0102017
- Queenstown Town Centre Masterplan ProgrammeQTS-0112017
- Queenstown Town Centre Arterials Business CaseQTS-2512017
- Queenstown Town Centre Parking Indicative BusinessQTS-0082017
- Queenstown Integrated Transport Programme BusinessQTS-0062017
- Queenstown Integrated Transport Programme BusinessQTS-0072017
Related news
- Queenstown cable car gets lift through AIP visa (leaves this site) (opens in new tab)NZ Government (Beehive) · 2026-10-06
- Landmark Regional Deal to shape future of Otago Central Lakes (leaves this site) (opens in new tab)Queenstown Lakes District Council · 2026-10-01
- Proposed $265m lending gives Queenstown cable car a lift (leaves this site) (opens in new tab)The Press · 2026-10-08
- Fresh calls for century-old Queenstown bridge to be replaced (leaves this site) (opens in new tab)1News (TVNZ) · 2026-09-14
- $150m debt deal brings Queenstown cable car closer to reality (leaves this site) (opens in new tab)Mountain Scene · 2026-09-05
- Quakes put spotlight on $81m Edith Cavell Bridge replacement (leaves this site) (opens in new tab)Mountain Scene · 2026-09-04
- National's South Island plan: Restrictions on data centres, Queenstown gondola funding, clearer river gravel rules (leaves this site) (opens in new tab)interest.co.nz · 2026-08-01
- National unveils South Island growth plan, includes funding plan for Queenstown gondola (leaves this site) (opens in new tab)Stuff · 2026-08-14