QTS-061 · Business case chapter or appendix · 2020
Wakatipu Basin Future Public Transport Demand Analysis – Technical Note 3b – Future Scenarios Update (Sept 2020)
Public source URL not yet recorded.
Part of: Rapid transit evidence →
WSP's Technical Note 3b sets out future-year public transport (PT) demand modelling for the Queenstown Town Centre, Frankton to Queenstown, and Frankton Transport Business Case, including outputs used in the business case economics and sensitivity tests for the Spatial Plan growth distribution and post-COVID-19 tourism. A bespoke logit-based spreadsheet PT model, fed by Abley's Tracks demand model, was run for 2018, 2028 and 2048 in three peak hours. Only two scenarios were tested with the updated demand: Do Minimum and the NZ Upgrade Programme (NZUP) package, which most closely represents the earlier 'Bus Max' option. The note records that a Mass rapid transit MRT scenario tested in the previous modelling round 'was omitted for implementability reasons', and that a Trackless Tram achieved the highest mode shift but was set aside for feasibility reasons. Results show NZUP keeps SH6A at 82-86% volume/capacity in 2028 while Do Minimum exceeds capacity; PT mode share on SH6A is around 45% at 2028 against around 20-25% at the Shotover and Kawarau Falls bridges. Demand is expected to approach or exceed capacity on SH6A by 2048 in all scenarios. The note concludes that parking control in the Town Centre is critical, that free parking in Frankton undermines PT, and that Ladies Mile land use and access do not sufficiently support PT. The Spatial Plan and COVID-19 sensitivity tests had limited impact on projected PT patronage.
What the document says
Context and purpose: Technical Note 3b (Final, Rev 2, 17 November 2020; WSP New Zealand) reports the methodology and results of future scenario modelling for the Queenstown Town Centre, Frankton to Queenstown, and Frankton Transport Business Case, including the outputs used in its economic evaluation and later sensitivity tests (p.1). It follows Technical Note 3 (model build) and Technical Note 3a (shortlist option testing) (p.1).
Method: Future demand comes from the Tracks model maintained by Abley Transportation Consultants on behalf of QLDC and Waka Kotahi, using 2028 and 2048 scenarios (pp.1-2). Two 2048 sensitivity sets were added: the preferred Spatial Plan growth distribution (more development near Jacks Point, 2,580 fewer jobs in the Queenstown urban area) and a post-COVID-19 set with reduced tourist activity (p.2). Car trips in the AM peak grow from 14,851 (2018) to 22,821 (2028) and 30,857 (2048) in the business case demand set (p.3). The spreadsheet model calculates mode share for each origin-destination pair and iterates with link travel times to convergence (p.3). Key assumptions include bus fare $2 and ferry $4.90, a mode penalty of $5 for bus and $7 for ferry, 40-seat buses (Bus Max services double-decker or articulated, capacity 100), airport passengers of 3.2m (2028) and 5.1m (2048), and Town Centre parking costs rising from $3.66 (2018 AM peak) to $13.78 (2028) and $20.66 (2048) (p.5). No active mode demand, peak spreading or TDM is modelled (pp.5-6). Park and ride sites are assumed at SH6/Howards Drive and SH6/Boyd Road (p.6). The note states the parking cost increase is 'a major driver in the increased PT model share' for Town Centre trips (p.6).
Scenarios: With the latest demand sets only Do Minimum and the NZUP scenario (closest to the earlier Bus Max option) were tested (p.3). NZUP uses a 'one-seat-ride' bus network, an improved Kelvin Heights-Town Centre bus-ferry link, and 'Virtual Priority' for buses on SH6A, with physical priority through Frankton Flats and a westbound Ladies Mile bus lane and bus gate (pp.3-4). Earlier option assessment had included Bus Min, Bus Max, Trackless Tram, Mass rapid transit MRT and ferry option; Bus Max was preferred (p.4).
Results: On SH6A in 2028, NZUP gives volume/capacity of 82-86% while Do Minimum exceeds capacity (p.7). For example, in the 2028 AM peak westbound the business case NZUP scenario carries 23% by bus and 13% by park and ride, against 15% by bus under Do Minimum (p.8). By 2048 demand 'is expected to reach close to, or exceed, capacity' on SH6A under all scenarios (p.7). PT mode share at the Shotover Bridge peaks at around 20% compared with around 45% on SH6A at 2028, attributed to dispersed Frankton land use, transfers and lack of Frankton parking control (p.10); at Kawarau Falls Bridge it peaks at around 25% (p.13). Spatial Plan and COVID-19 sensitivity sets had 'limited impact on projected public transport patronage' (p.16). At 75% of the assumed parking cost, the degree of saturation on Frankton Road approaches 100% (p.16).
Conclusions: NZUP retains a high degree of mode shift over Do Minimum, particularly at 2048; 'sticks' such as parking control 'appear to be critical'; the land use and first/last mile access assumed on Ladies Mile does not sufficiently support PT; and southern housing areas should be designed with PT as a priority (p.16). Appendices (pp.17-50) give the NZUP PT network, hub passenger movements and origin-destination matrices by mode, including MRT columns that are zero throughout.
Mass rapid transit: The note records that 'An additional scenario, Gondola MRT, was tested under the previous round of demand sets but was omitted for implementability reasons before this update' (p.3). It lists Mass rapid transit MRT, ferry option and Trackless Tram among previously tested High Capacity Public Transport scenarios, says the Trackless Tram 'achieved the highest mode shift' but feasibility issues led to Bus Max being preferred, and that only Bus Max (NZUP) was tested with updated demand (p.4). It gives no mass rapid transit results and does not explain the implementability reasons. Model output tables carry an MRT mode row with zero trips (pp.8-15, 21-50).
Key figures
- AM peak car trips: 14,851 (2018), 22,821 (2028), 30,857 (2048) business case demand set (p.3)
- Town Centre parking cost (AM inbound): $3.66 (2018), $13.78 (2028), $20.66 (2048) (p.5)
- Bus fare $2, ferry $4.90; mode penalty $5 bus, $7 ferry (p.5)
- Airport passengers assumed 3.2m (2028) and 5.1m (2048) (p.5)
- SH6A v/c under NZUP 82%-86% in 2028; Do Minimum exceeds capacity (p.7)
- 2028 AM peak westbound SH6A, business case NZUP: bus 23%, park and ride 13%, car 62% (p.8)
- PT mode share around 45% on SH6A at 2028; max around 20% at Shotover Bridge and around 25% at Kawarau Falls Bridge (pp.10, 13)
- 2048 Do Minimum demand exceeds SH6A capacity by up to 18% (interpeak eastbound) (p.7)
- At 75% of assumed parking cost, Frankton Road degree of saturation approaches 100% (p.16)
Rapid transit
Mass rapid transit means light rail, gondola/cable car, bus rapid transit and similar dedicated rapid-transit technologies. It does not include ordinary bus services or ferries.
Passing. Mentions mass rapid transit without assessing it.
Records a mass rapid transit scenario tested earlier but omitted for 'implementability reasons'; only the Do Minimum and the NZUP bus package were modelled with updated demand. That bus package is not mass rapid transit. A ferry scenario in the earlier set is not mass rapid transit either.
The note states that 'An additional scenario, Gondola MRT, was tested under the previous round of demand sets but was omitted for implementability reasons before this update' (p.3). It lists the High Capacity Public Transport scenarios from the business case option assessment as Bus Min, Bus Max, Trackless Tram (or similar road-based higher capacity rapid transit), Mass rapid transit MRT and ferry option, and says earlier modelling 'helped to identify Bus Max as the preferred option' (p.4). It notes that the Trackless Tram 'achieved the highest mode shift because of a lower mode penalty' but that feasibility issues led to Bus Max being preferred, so 'only the Bus Max option (now the PT assumptions within the NZUP package) was tested with the updated demand sets' (p.4). No mass rapid transit patronage or results are reported, and the implementability reasons are not set out. The MRT rows in the point summaries and appendix matrices show zero trips because no MRT mode was included in the scenarios tested (pp.8-15, 21-50). The note also finds SH6A demand close to or above capacity by 2048 in all tested scenarios (p.7).
"An additional scenario, Gondola MRT, was tested under the previous round of demand sets but was omitted for implementability reasons before this update." (p.3) | "The Trackless Tram option achieved the highest mode shift because of a lower 'mode penalty' but is largely interchangeable with the Bus Max option in terms of infrastructure. Feasibility issues with the Trackless Tram option led to Bus Max being preferred." (p.4) | "Notably, demand is expected to reach close to, or exceed, capacity in 2048 under all scenarios, even with more stringent parking controls and improvements to public transport." (p.7)
Files
- Open Main document (PDF, 6.7 MB) Opens in a new tab.
Main document
Actions recorded
Apply parking control ('sticks') alongside PT improvements, including addressing unrestricted free parking in Frankton, to achieve mode shift.
Not assessed
"sticks" such as parking control appear to be critical
Design southern housing areas with public transport as a priority to future-proof the transport system serving the area.
Not assessed
emphasises the need to ensure housing areas to the south are designed with public transport as a priority
Study cost
A study cost has been requested under the Official Information Act or LGOIMA. No figure has been received.
Citation
Wakatipu Basin Future Public Transport Demand Analysis – Technical Note 3b – Future Scenarios Update (Sept 2020) (2020).