Abley slide presentation, dated 21 March 2018, summarising the Queenstown Integrated Transport Programme Business Case (QITPBC) prepared for partners NZTA, QLDC, ORC and Queenstown Airport Corporation. It covers PBC development, the evidence base (problem statements weighted 67% and 33%, traffic growth on SH6/SH6A, airport and tourism growth, Thinkplace liveability findings, mode share and parking occupancy), the nine programmes assessed and the selection of the Balanced PT and Active Modes Focus programme. A peak hour demand versus capacity chart for SH6A adds water taxis from 2019, PT Stage 2 and ferries from 2023, and 'MRT 2040'. A map shows an indicative MRT corridor 'Beyond 2027'. Stated outcomes are 30% alternative mode share (up from 15%), a 16-minute Queenstown-Frankton travel time reduction and 3-minute variability in the 2045 AM peak. Conclusions stress partner commitment, the 'potential role of alternative funding mechanisms (e.g. MRT)', the risk that private vehicle use does not fall, and inter-agency alignment.

What the document says

Context. This 21-slide deck by Abley, with contact details for Dave Smith (p.21), presents the Queenstown Integrated Transport Programme Business Case (QITPBC). The footer dates it 21 March 2018, nine months after the business case (Version 4, 16 June 2017). Slide 3 lists the PBC partners as NZTA, QLDC, ORC and QAC; the audience and venue are not stated.

Evidence base. Problems and benefits are restated: growth causing trip unreliability and worse customer experience (67%) and car dominance affecting liveability (33%) (p.4). A traffic table shows 2012 to 2016 AADT growth, e.g. SH6A west of Frankton about 17,863 to 23,925 vehicles per day (p.5). Further slides show airport passenger and tourism spend trends (p.6), SH6A and SH6 traffic against theoretical capacity (pp.7-8), projected households and jobs to 2045 (p.9), Thinkplace survey findings that journey times are unpredictable and public transport is 'expensive, unreliable and infrequent' (p.10), 7am-11am mode share to the town centre (overall about 77% car occupants and 13% public transport) and 2016 parking occupancy of about 87-92% at midday (p.11).

Programme development. Nine programmes were developed, from Do Minimum to Do Maximum (p.12); a programme assessment slide traces Balanced 1 to the selected 'Balanced PT & Active Modes Focus' (p.13). A map shows the recommended programme, with an 'MRT Corridor (Indicative)' between Frankton and the town centre labelled 'Beyond 2027' (p.14). An SH6A peak hour demand versus capacity chart (persons per hour, 2016-2048) shows road, PT, water taxi and MRT capacity against low, expected and high growth, with 'Water Taxis 2019', 'PT Stage 2 and Water Ferries 2023' and 'MRT 2040' (p.15). The recommended programme timeline places the MRT corridor at '2027 or beyond' (p.16). A version of the chart adds a line annotated '5% growth per annum?!' (p.17), and a further slide is headed 'Recommended Programme delivered earlier' (p.18). Stated outcomes are 30% alternative mode share (up from 15%), a 16-minute travel time reduction between Queenstown and Frankton and 3-minute variability in the 2045 AM peak (p.19).

Conclusions (p.20): partner commitment is critical; 'Potential role of alternative funding mechanisms (e.g. MRT)'; the key risk is that the reduction in private vehicle use is not achieved; agencies must integrate and align; and the PBC provides a foundation for district transport planning (e.g. the GR2KB DBC).

Mass rapid transit: The deck shows an indicative MRT corridor from Frankton to the town centre 'Beyond 2027' (p.14), MRT capacity added to SH6A in 2040 (p.15), and MRT as an example of alternative funding (p.20). Slides 17-18 suggest that faster growth (5% a year) would bring the need, and the programme, forward, but the deck gives no explanation in text.

Key figures

  • Problem weighting: trip unreliability 67%, car dominance 33% (p.4)
  • SH6A west of Frankton AADT about 17,863 (2012) to 23,925 (2016) (p.5)
  • 7am-11am town centre mode share about 77% car occupants, 13% public transport (p.11)
  • 2016 parking occupancy: on-street 89% (10am), 87% (1pm); off-street 91%, 92% (p.11)
  • Outcomes: 30% alternative mode share (up from 15%); 16-minute Queenstown-Frankton travel time reduction; 3-minute variability in 2045 AM peak (p.19)
  • MRT capacity shown on SH6A from 2040 (p.15)

Rapid transit

Mass rapid transit means light rail, gondola/cable car, bus rapid transit and similar dedicated rapid-transit technologies. It does not include ordinary bus services or ferries.

Substantive. Discusses, assesses, recommends or programmes mass rapid transit.

Shows indicative Frankton-town centre MRT corridor beyond 2027, MRT capacity on SH6A from 2040, and MRT as alternative funding example

MRT appears in three places. The recommended programme map shows an 'MRT Corridor (Indicative)' linking Frankton and the Queenstown town centre, labelled 'Beyond 2027' (p.14), and the programme timeline lists 'MRT corridor' under 'Long Term 2027 or beyond' (p.16). The 'SH6A Peak Hour Demand vs Capacity' chart adds MRT capacity labelled 'MRT 2040' on top of road, public transport and water taxi capacity, set against low, expected and high growth (p.15); a second version adds a line annotated '5% growth per annum?!' rising to meet the MRT capacity around 2040 (p.17), followed by a slide headed 'Recommended Programme delivered earlier' (p.18). The conclusions list 'Potential role of alternative funding mechanisms (e.g. MRT)' (p.20). The mode is not named in the slide text.

"Potential role of alternative funding mechanisms (e.g. MRT)" (p.20) | "MRT 2040" (p.15) | "MRT Corridor (Indicative)" (p.14) | "5% growth per annum?!" (p.17)

Files

Actions recorded

No actions are recorded on this document.

Study cost

Costed with the parent document.

Citation

Queenstown Integrated Transport Programme Business Case (2018).