QTS-047 · Business case chapter or appendix · 2020

Appendix E Financial Case - Appendix E1 Funding Spreadsheet

Part of: Rapid transit evidence →

Appendix E1 is the funding spreadsheet for the Financial Case of the NZUP Queenstown Transport Business Case, published by NZTA (Waka Kotahi). It sets out a nine-year (2021-2029) cash flow by project, phase and funder. The element total is $600.76 million (p.7), with a further $12.46 million of items excluded from the charts. By funder (p.8): NZUP committed $107.48m; Crown Infrastructure Partners committed $119.70m (Crown and QLDC); Waka Kotahi $26.02m; QLDC $151.94m; ORC $269.50m; total $674.64m. This funder table does not account for the 50% QLDC-ORC cost share for the Stanley Street and Frankton hubs, which appear in both councils' totals. ORC's share is dominated by PT capex (new bus fleet $46m, depot $34m) and gross PT opex of $126.59m. Footnotes state that 'Offline PT Service Improvements' are 'under further investigation beyond 2030 ($262M)' and Arterial Stage 3 likewise ($61.2M). Neither is in the funded cash flow.

What the document says

Context: Appendix E1 is an eight-page spreadsheet print (pp.1-2 are dividers). Funding is listed by funder:

1. NZUP (Committed), p.3: SH6A corridor improvements $26,739,506; Grant Road to Kawarau Falls Bridge improvements $68,707,588, incl. interim Frankton Hub $12.8m and SH6/6A intersection; Ladies Mile Stage 2 $11,258,124; ITS (SCATS Priority Engine $50k; VMS $720k) $770,000. Total $107,475,218, spread over 2021-2024.

2. CIP (Committed), 'Includes Crown and QLDC', p.4: Arterials Stage 1 $59,701,969; Town Centre Street Upgrade Stage 1 $60,000,000 (streetscapes 'to Skyline Gondola'). Total $119,701,969.

3. Waka Kotahi, p.4: Travel Behaviour Change SSBC $300,000; Stanley/Shotover Street improvements $25,280,941; bus lane enforcement cameras $400,000; SCATS maintenance $40,000. Total $26,020,941.

4. QLDC, p.5: Town Centre Improvements Stage 2 $30,798,998; Arterial Stage 2 $48,796,021 (2027-2029); Stanley Street full hub $45,933,120 and Frankton hub $15,485,483 (each '50% cost share with ORC'); Frankton local works incl. Humphrey Street Link $10,924,928. Total $151,938,550. Footnote: ''Arterial 3' is under further investigation beyond 2030 ($61.2M)'.

5. ORC, p.6: Stanley Street and Frankton hubs (50% share with QLDC, shown at full value); PT Services and Infrastructure DBC $1,500,000; new bus fleet $46,000,000 and new bus depot $34,000,000 (2027-2029); PT services within the existing contract $55,062,426; the on-road PT service step change $71,522,958 (2027-2029). Total $269,503,987.

Footnotes on p.6: ''Offline PT Service Improvements' is under further investigation beyond 2030 ($262M)'; the existing contract cost for 2021-24 is not part of the business case; and the step change is a 'Continuous programme beyond 2030 until 2051 ($5.5M average)'.

Cash flow by element (p.7): the total is $600,757,134. Annual totals peak at $115.4m in 2028. Excluded from the charts are the PT DBC, SCATS ongoing costs and the Frankton local works, totalling $12,464,928. A note repeats that Arterial 3 ($61.2M) and Offline PT Service Improvements ($262M) are under further investigation beyond 2030.

Cash flow by organisation (p.8): $674,640,665 in total. The note says the table 'does not take into account the 50% cost share between QLDC and ORC' for the two hubs.

Mass rapid transit: The only MRT item is the footnote line ''Offline PT Service Improvements' is under further investigation beyond 2030 ($262M)', placed in the ORC section (p.6) and repeated in the cash flow note (p.7). It has no funder, phase or year, and it is outside the $600.76m funded cash flow. 'Skyline Gondola' appears only as the end-point of town centre streetscape upgrades (p.4).

Key figures

  • Total cash flow by element 2021-2029: $600,757,134 (p.7)
  • Funding by party (p.8): NZUP (Committed) $107,475,218; CIP (Committed, Crown and QLDC) $119,701,969; Waka Kotahi $26,020,941; QLDC $151,938,550; ORC $269,503,987; total $674,640,665 (hub 50% shares not netted)
  • Offline PT Service Improvements $262M - further investigation beyond 2030 (p.6)
  • Arterial Stage 3 $61.2M - further investigation beyond 2030 (p.5)
  • ORC PT capex: new bus fleet $46,000,000; new bus depot $34,000,000 (p.6)
  • ORC PT opex (gross) 2021-2029 $126,585,384, incl. on-road step change $23,840,986 a year from 2027 (p.6)
  • Stanley Street full hub $45,933,120; Frankton hub $15,485,483 (50% QLDC / 50% ORC) (pp.5-6)
  • Items excluded from charts: $12,464,928 (p.7)

Rapid transit

Mass rapid transit means light rail, gondola/cable car, bus rapid transit and similar dedicated rapid-transit technologies. It does not include ordinary bus services or ferries.

Passing. Mentions mass rapid transit without assessing it.

Offline PT ($262M) listed only as under further investigation beyond 2030; not funded or allocated to any party

The spreadsheet's only offline PT entry is a footnote in the ORC section: ''Offline PT Service Improvements' is under further investigation beyond 2030 ($262M)' (p.6). It is repeated in the element cash flow note: 'Arterial 3 ($61.2M) and Offline PT Service Improvements ($262M) are under further investigation beyond 2030' (p.7). The item has no cash flow, funder or phase and is excluded from the $600,757,134 nine-year total (p.7) and from the $674,640,665 funder summary (p.8). The funded PT programme is on-road: a new bus fleet ($46m), a depot ($34m) and gross PT opex ($126.59m) to 2029, with the step-change service continuing 'beyond 2030 until 2051' (p.6).

"'Offline PT Service Improvements' is under further investigation beyond 2030 ($262M)" (p.6) | "Arterial 3 ($61.2M) and Offline PT Service Improvements ($262M) are under further investigation beyond 2030." (p.7)

Files

Actions recorded

  • Deliver NZUP SH6A corridor improvements (intersections, bus lanes, bus stops, shared path, supporting PT infrastructure): $26.74m

    Not assessed · NZTA · 2021-2024

    Total for NZUP SH6A Corridor Improvements $ 26,739,506

  • Deliver NZUP Grant Road to Kawarau Falls Bridge improvements incl. interim Frankton Hub and SH6/6A intersection: $68.71m

    Not assessed · NZTA · 2022-2024

    Total for NZUP Grant Road to KF Bridge Improvements $ 68,707,588

  • Deliver NZUP SH6 Ladies Mile Stage 2 (westbound bus lane, Howards Drive roundabout): $11.26m

    Not assessed · NZTA · 2022-2024

    Total for NZUP SH6 Ladies Mile Stage 2 $ 11,258,124

  • Install ITS: SCATS Priority Engine software ($50k) and variable message signs ($720k)

    Not assessed · NZTA · 2021-2024

    Total for ITS $ 770,000

  • Deliver Arterials Stage 1: $59.70m

    Not assessed · QLDC · 2021-2023

    Total for Arterials - Stage 1 $ 59,701,969

  • Deliver Town Centre Street Upgrade Stage 1 (full streetscape upgrades incl. Park, Camp, Rees, Beach, Man/Brecon Streets to Skyline Gondola): $60m

    Not assessed · QLDC · 2021-2023

    Total for Town Centre Street Upgrade - Stage 1 $ 60,000,000

  • Prepare a Travel Behaviour Change single stage business case ($300k)

    Not assessed · NZTA · 2021

    Travel Behaviour Change SSBC Single Stage Business Case $ 300,000

  • Deliver Stanley Street and Shotover Street improvements (interim hub, PT improvements, Shotover to Arterial 1): $25.28m

    Not assessed · NZTA · 2021-2026

    Total for Stanley Street and Shotover Street Improvements $ 25,280,941

Show all 19 actions
  • Install bus priority lane enforcement cameras ($400k)

    Not assessed · NZTA · 2024

    Bus priority lane enforcement infrastructure (cameras) Implementation $ 400,000

  • Deliver Town Centre Improvements Stage 2 (Lake Esplanade without bus lanes, Ballarat, Camp, Church, Earl, Marine Parade, ped crossings): $30.80m

    Not assessed · QLDC · 2022-2027

    Total for Town Centre Improvements (Stage 2) $ 30,798,998

  • Deliver Arterial Stage 2 (Gorge Road to Hay Street link, Brecon St steps, Camp-Man intersection): $48.80m

    Not assessed · QLDC · 2027-2029

    Total for Arterial Stage 2 $ -... $ 48,796,021

  • Deliver Stanley Street full bus hub ($45.93m), 50% cost share between QLDC and ORC

    Not assessed · QLDC · 2028-2029

    Stanley Street - full hub improvements (50% cost share with ORC)

  • Deliver Frankton transport hub ($15.49m), 50% cost share between QLDC and ORC

    Not assessed · QLDC · 2028-2029

    Frankton hub (50% cost share with ORC)

  • Deliver Frankton local works incl. Humphrey St Link (SH6 to Lucas Place): $10.92m (excluded from cash flow charts)

    Not assessed · QLDC · 2023-2027

    Total for Frankton $... $ 10,924,928

  • Prepare a PT Services and Infrastructure Detailed Business Case ($1.5m)

    Not assessed · ORC · 2021-2022

    PT Services and Infrastructure DBC Detailed Business Case $ 750,000 $ 750,000

  • Procure a new bus fleet ($46m) and new bus depot ($34m)

    Not assessed · ORC · 2027-2029

    New bus fleet Implementation... $ 46,000,000; New bus depot... $ 34,000,000

  • Fund PT service improvements within the existing contract ($55.06m) and the on-road PT service step change from 2027 ($71.52m; continuing to 2051 at ~$5.5m average)

    Not assessed · ORC · 2021-2029 and beyond to 2051

    On Road PT Service Improvements (step change)

  • Further investigate Offline PT Service Improvements ($262M) beyond 2030

    Not assessed · Beyond 2030 · Relevant to rapid transit

    'Offline PT Service Improvements' is under further investigation beyond 2030 ($262M)

  • Further investigate Arterial Stage 3 ($61.2M) beyond 2030

    Not assessed · Beyond 2030

    'Arterial 3' is under further investigation beyond 2030 ($61.2M)

Study cost

A study cost has been requested under the Official Information Act or LGOIMA. No figure has been received.

Citation

Appendix E Financial Case - Appendix E1 Funding Spreadsheet (2020).