Current plans · NZTA
NZ Transport Agency Waka Kotahi (NZTA): current plans for Queenstown
Last updated:

Position as at 19 October 2026. Every figure is cited to a document ID in the evidence base, with the page number. Page numbers are PDF page numbers unless marked "printed".
Overview
NZTA owns and manages the state highways through the Whakatipu Basin: SH6 (Kawarau Rd, Frankton–Ladies Mile Highway) and SH6A (Frankton Rd). It also co-funds QLDC and ORC transport activities through the National Land Transport Fund (NLTF). Its current work in Queenstown has two parts:
- The Queenstown Package (Kā Huanui a Tāhuna). This is the construction programme at Frankton, at the SH6/Howards Dr intersection and at the Pūāhuru walking and cycling bridge, delivered by an alliance of NZTA, QLDC, Beca, WSP, Downer and Fulton Hogan [QTS-164 p.1–2].
- The Queenstown Strategic Network Plan (QSNP). This is a 30-year, phased plan for the state highway network, published in August 2026 [QTS-130] and released by the Minister of Transport on 6 October 2026 [QTS-138].
Queenstown Strategic Network Plan: NZTA governance, June to August 2026 (released under OIA-23524)
As at
NZTA released these records on 16 October 2026 under the Official Information Act 1982 (OIA-23524) [QTS-226]. They record how the Queenstown Strategic Network Plan moved through NZTA's committees and Board between June and August 2026.
| Date | Record |
|---|---|
| 12 Jun 2026 | NZTA Board strategic transport planning workshop: cover paper (QTS-219), pre-read pack (QTS-218), slides (QTS-220); the optioneering technical memo (QTS-221) is dated the same day |
| 9 Jul 2026 | Value, Outcomes & Scope Committee recommends that the Board endorse the QSNP (QTS-222) |
| 12 Aug 2026 | Board paper for endorsement (QTS-223) and QSNP summary attachment (QTS-224); the Board endorses the QSNP (QTS-225) |
| 16 Oct 2026 | NZTA OIA-23524 response (QTS-226) |
Differences between the documents
- Gondola wording. The June pre-read and slides (QTS-218 p.8, QTS-220 p.6) say "Long term: Offline PT (e.g. gondola) is the only remaining viable option" for Frankton to Town Centre. The August Board paper (QTS-223 p.2) says an off-line public transport system will be required and "The QSNP is agnostic to the technology". The technical memo (QTS-221) says the plan "does not specify a preferred technology, alignment or operating model". The Board minute (QTS-225) records "various alternative proposals, including gondolas" and NZTA's approach "to get ready to participate in the assessment of the gondola proposals".
- Visitor-growth impact. The same 0.5% a year reduction is costed differently. The June pre-read gives an NPV of $5.4b over 40 years (QTS-218 p.5). The August paper and summary give $3.9b NPV over 40 years (QTS-223 p.2; QTS-224).
- Cost ranges. The technical memo and Board paper give about $1.4–2.6b capital over 30 years (QTS-221; QTS-223 p.2, plus $11m–$25m a year PT opex). The committee minutes and the summary give $1.5–2.5b (QTS-222 p.3; QTS-224 p.5). Within the memo, the offline public transport spine is indicatively $500m–1.0bn.
- Corridor protection. The QSNP summary lists "Protect future high-capacity corridors" as an implementation action (QTS-224 p.3). The OIA response states "there has been no consideration to protecting or designating corridors" (QTS-226 p.6), and that new delivery, funding and financing approaches "have not been investigated".
NZUP Queenstown Package, 2020–2024
Records from 2020 to 2024 (QTS-210 to QTS-217) and the OIA response (QTS-226) set out the NZ Upgrade Programme Queenstown Package. QTS-226 pp.4–5 gives the $250m budget as:
| Item | Amount |
|---|---|
| Business case and other pre-programme costs | $2.217m |
| Property acquisition | $14.451m |
| Pre-implementation | $35.324m |
| Implementation (construction) | $188.446m |
| NZTA indirect costs | $9.56m |
| Total | $250m |
The letter says $107.6m was the compilation of individual activity costs (QTS-210), $115m the original allocation including NZTA indirect costs, and $130m after a $15m escalation allocation. It also says the mass rapid transit gondola was not part of the NZUP Queenstown Package.
Benefits Realisation Plan targets (QTS-217 p.2; 2024 baseline to 2030 target):
| Measure | 2024 baseline | 2030 target |
|---|---|---|
| Peak-hour bus movements through Frankton bus hub | 20 | 40 |
| AM peak-hour PT passengers on SH6A | 260 | 970 |
| Bus reliability | 79% | 95% |
| Bus punctuality | 41% | 95% |
| Maximum daily vehicle movements through SH6/SH6A intersection | 42,000 | 48,000 |
Records in this release
- Optioneering technical memo (QTS-221)
- QSNP summary attachment (QTS-224)
- Board minute endorsing the QSNP (QTS-225)
- Value, Outcomes & Scope Committee minutes (QTS-222)
- Board workshop pre-read pack (QTS-218)
- Board workshop slides (QTS-220)
- Board paper for endorsement (QTS-223)
- NZTA OIA-23524 response (QTS-226)
1. Queenstown Package (under construction)
Budget history
| Item | Figure | Source |
|---|---|---|
| Budget originally approved (2020) | $107.6m | QTS-113 p.1 |
| Revised budget (adds NZTA core costs and pre-2020 costs) | $115m | QTS-113 p.1 |
| Alliance reconciled delivery price (excludes business case, property, alliance management, consenting and NZTA core/direct costs) | $329.97m | QTS-113 p.1 |
| Consolidated and renamed the "RoRS Queenstown package" | $250m budget | QTS-113 p.2 |
| Project page, Estimated project cost | $250 million funding | QTS-164 (captured ) |
Scope
The original design scope had seven items, (a) to (g). The OIA response says: "While all the above were designed, only items a, b, and c were funded to progress to construction in 2024. Robust cost estimates have not been developed for the elements that have not progressed to construction." [QTS-113 p.2]
| Item | Description | Status (QTS-113 p.2) |
|---|---|---|
| a | Five signalised intersections at Frankton: SH6/SH6A, SH6/Joe O'Connell Dr, SH6/Bus Hub exit, SH6/Bus Hub entry, SH6A/McBride St | Funded, under construction |
| b | New and expanded Frankton bus hub | Funded, under construction |
| c | New intersection at SH6/Howards Dr (originally a roundabout) | Funded, under construction (now signals; see below) |
| d | Four signalised intersections and three pedestrian signals on SH6A, Frankton–Queenstown | Designed, not funded for construction |
| e | Signals at Hawthorne Dr and Grant Rd; pedestrian signals near Hardware Lane | Designed, not funded for construction |
| f | Humphrey St and Lucas Place roundabouts converted to signals; pedestrian signals relocated near Ross St (southern corridor) | Designed, not funded for construction |
| g | SH6 Ladies Mile eastbound bus lane, Howards Dr to Shotover bridge | Designed, not funded for construction |
Progress and timing
As at
Overall programme
- Construction is expected to take four years and is "1/3 of the way through" [QTS-164].
- Phase 3 runs from winter 2026 to summer 2027, and Phase 4 from summer 2027 to spring 2028. Phase 5 (spring to winter 2028) is "whole intersection operational" (NZTA construction phases (opens in new tab), accessed ).
- ORC reports the Frankton works are "forecast to be completed in mid-2028, doubling the Hub's capacity" [QTS-151 p.266].
Frankton intersection and Bus Hub
- Temporary roundabout: a temporary roundabout at the SH6/6A intersection was planned for around March 2026, so the northern side of the highway could be rebuilt [QTS-140 p.6].
- Bus Hub: the new southern end was scheduled to become operational in about May 2026 [QTS-140 p.7]. It opened on 25 June 2026 (NZTA Journey Planner bulletin, 25 Jun 2026).
- Electricity cabling: 6,429m of 6,464m was complete by December 2025 [QTS-140 p.2].
- Works in August 2026: the Frankton Village carpark (903 sq m), and kerb and channel work towards the Hansen Rd link [QTS-141 p.2, p.4].
- Hansen Rd link: due to open in October 2026, when the end of the current Hansen Rd becomes a cul-de-sac [QTS-141 p.4].
SH6/Howards Dr
- The intersection "is being rebuilt as traffic signals": a four-leg signalised intersection with 150m of shared path. The speed limit is 50km/h for the "18 month construction period", and the notice is captioned "Visualisations upon completion early 2028" [QTS-143 p.1].
- The project page says main construction starts in mid 2026, will take about 18 months, and the new intersection "is expected to be in place by summer 2027/28" [QTS-163].
- The Minister's release confirms signalisation and "a fourth leg… to help accommodate much-needed housing" [QTS-138].
Pūāhuru walking and cycling bridge
- Funding and contract: $12.6m approved; contract awarded to the Kā Huanui a Tāhuna alliance; completion by the end of 2027 [QTS-147].
- Design: a single span of about 51.7m with a 3m shared path, connecting Jim's Way and Ferry Hill Dr to Hardware Lane. QLDC will improve crossings at Tucker Beach Rd, Hawthorne Dr and Grant Rd. (NZTA Pūāhuru bridge (opens in new tab), accessed )
- Early works: soil nailing is under way (about six months, up to 70 nails), with a temporary 50km/h limit over 1.2km [QTS-141 p.5].
- Traffic: SH6 at this point carries about 27,000 vehicles per day [QTS-147].
2. Queenstown Strategic Network Plan (QTS-130, August 2026)
Phasing and cost bands [QTS-130 p.44]
| Phase | Label | Timeframe |
|---|---|---|
| 1 | Foundation for change | 1–3 years |
| 2 | Incremental capacity | 3–10 years |
| 3 | Capacity step change | 10–30 years |
The plan's indicative cost bands are: $ = <$10m; $$ = $10–99m; $$$ = $100–249m; $$$$ = $250–999m; $$$$$ = $1bn+.
Staged programme (Figure 16) [QTS-130 p.44]
- Stage 1: (1) Frankton Flats bus priority and active modes; (2) intersection and capacity upgrades at Frankton Flats.
- Stage 2: (3) Ladies Mile intersections; (4) Ladies Mile bus priority and active modes; (5) Southern Corridor intersections and bus priority; (6) SH6A active modes and bus stops; (7) town centre bus hub; (8) park and ride; (9) SH6A intersections.
- Stage 3: (10) Frankton–Queenstown offline public transport; (11) Frankton–Ladies Mile offline public transport; (12) a new Kawarau River crossing (road or offline public transport); (13) capacity upgrades on the Southern Corridor.
Selected activities from the corridor tables [QTS-130 Tables 11–15, pp.45–54]
| Activity | Cost band | Page |
|---|---|---|
| Frankton Flats signalised intersections (Hawthorne, Grant, Lucas Place) | $$$ | pp.47–48 |
| Frankton Flats bus lanes | $$ | pp.47–48 |
| Frankton Flats active modes | $ | pp.47–48 |
| New Kawarau River crossing | $$$$ | pp.49–50 |
| Frankton–Queenstown offline public transport line (technology to be confirmed… Progress investment case or integrate aligned private proposal) | $$$ | pp.51–52 |
| Frankton offline public transport central hub (Central Frankton interchange for a future offline public transport spine) | $$$ | pp.47–48 |
| Time-of-use charging | $ | p.54 |
Other parts of the plan
- Non-state-highway activities: these include replacing Edith Cavell Bridge [QTS-130 Table 16, p.55].
- Alternative funding: set out in Table 17 [QTS-130 p.56].
- Funding responsibility: the plan notes this is not allocated activity by activity [QTS-130 p.42].
- Role in investment: the QSNP is the primary input to the State Highway Investment Proposal and the NLTP [QTS-130 p.57].
Immediate next steps, QSNP Table 19 [QTS-130 pp.58–59]
| Next step | Indicative cost stated |
|---|---|
| Frankton Flats Network Improvements | $250m (can be staged) |
| Ladies Mile Corridor Improvements | $0.75m–$1m |
| Southern Corridor Early Interventions | $0.75m–$1m |
| Arthurs Point Crossing (QLDC-led) | $60m–$80m (assumes 51% funding assistance rate) |
| Offline public transport: investment case, including relationship with any private sector proposals | $1m–$2m |
| Time-of-use charging | $1m–$2m |
| Alternative funding and financing | Workstream; no cost stated |
3. Minister of Transport's release, 6 October 2026 [QTS-138]
Growth and outcomes
- Peak-day population is expected to grow from about 83,000 (2025) to about 143,000 (2055).
- The release sets three core outcomes: make best use of existing infrastructure; move more people in less space, "including buses and gondolas or cable cars"; and actively manage demand.
Early priorities
- Frankton Flats intersection, capacity and bus priority.
- Ladies Mile and Southern Corridor upgrades.
- Town centre bus hub improvements.
- Walking and cycling connections.
- Replacing Edith Cavell Bridge.
Longer term
- The release says longer-term projects "may include 'offline high-capacity public transport', such as the gondolas or cable cars, with several private sector proposals already under discussion."
- An additional Kawarau River crossing is proposed in the longer term.
Edith Cavell Bridge: NZTA is in discussions with QLDC on replacing the bridge, "with funding to be considered in due course".
Use of the QSNP: it will feed into regional land transport and public transport plans, into QLDC's Mayoral Transport Taskforce, and into consideration for the 2027–30 NLTP.
4. Funding documents in force
NLTP 2024–27 (QTS-098)
- Public transport services: the $136m of PT service improvements includes "$5 million for Queenstown" [QTS-098 p.29].
- Otago entries: these list the Queenstown Package (Road of Regional Significance), covering SH6A corridor improvements, the SH6 and 6A Frankton intersection improvements and SH6 improvements including a bus hub. They also list resilience works on SH6 Cromwell–Frankton and Frankton–Kingston [QTS-098 p.79].
- Shepherds Hut Creek culvert, Queenstown: $2.176m [QTS-098 p.20].
Otago Southland RLTP 2021–31, mid-term review 2024 (QTS-148; in force until the RLTP 2027–37 replaces it)
- SH6 Frankton Flats network improvements: property $5.3m in each of 2025/26 and 2026/27; implementation $32.7m (2026/27) and $98.1m over 2024–30. This "supports NZUP Queenstown package i.e. KFB to Ross St and Hansen Road to Hardware Lane corridor improvements" [QTS-148 p.71].
- Stanley St Corridor Improvements (NZTA): pre-implementation $1.308m, property $2.12m and implementation $35.098m over 10 years [QTS-148 p.81]. Regional priority 11 [QTS-148 p.71].
- NZTA low-cost, low-risk PT infrastructure: $650k a year, $1.95m over 2024–27 [QTS-148 p.79].
- "SH6/6A Queenstown Offline High Capacity PT IMP": this was "removed from the State Highway Investment Proposal 2024–34 due to other priorities set out in the GPS and the likelihood of obtaining funding in the next three years". It had been ranked #2, and the RTCs record that they "are disappointed that this project has been removed" [QTS-148 p.79].
5. Otago Central Lakes Regional Deal: NZTA commitments (signed 6 October 2026, QTS-139)
As at
Outcome 7, Reliable Transport [QTS-139 pp.24–26]
- NZTA will progress the Whakatipu Strategic Network Plan initiatives: offline mass rapid transit alongside bus; second Kawarau and Shotover crossings; and time-of-use charging, parking and demand management.
- NZTA will work with QLDC on funding, financing and procurement tools, and will take the RLTP prioritisation into account.
- The deal sets out an Otago Central Lakes Transport Network Plan.
- The deal names priority projects: the Ladies Mile/Howards Dr intersection, expansion of Frankton Flats, and the next stage of PT upgrades.
- The deal states that GPS 2027 will reflect the deal's priorities, and that the GPS 2027 PT activity class definitions will not exclude offline mass rapid transit or ropeways.
No new Crown money in the first three years: "during the first three years… no additional funding is expected to be made available under Central Government Budgets" [QTS-139 p.5, cl.2.1(d)].
Figures
| Project | Lead | Status | Budget | Timing | Source |
|---|---|---|---|---|---|
| Queenstown Package (Kā Huanui a Tāhuna) – overall | NZTA with QLDC (alliance: Beca, WSP, Downer, Fulton Hogan) | Under construction; '1/3 of the way through' (project page) | $250m budget (RoRS package); originally $107.6m (2020), revised $115m; alliance reconciled delivery price $329.97m excl. other costs | 4-year construction; Phase 5 'whole intersection operational' spring–winter 2028; ORC: Frankton works forecast complete mid-2028 | QTS-113 pp.1–2; QTS-164; NZTA construction phases page; QTS-151 p.266 |
| (a) Frankton signalised intersections: SH6/SH6A, SH6/Joe O'Connell Dr, SH6/Bus Hub exit & entry, SH6A/McBride St | NZTA | Under construction (temporary roundabout from ~Mar 2026) | Within $250m package | To 2028 | QTS-113 p.2; QTS-140 p.6 |
| (b) Frankton Bus Hub expansion | NZTA | New southern half opened 25 Jun 2026; northern end being upgraded | Within $250m package | Hub capacity doubled on completion (mid-2028) | QTS-140 p.7; NZTA Journey Planner 25 Jun 2026; QTS-151 p.266 |
| (c) SH6 Ladies Mile / Howards Dr intersection (now 4-leg signals; originally roundabout) | NZTA | Under construction from mid 2026 | Within $250m package | ~18 months; 'in place by summer 2027/28' (project page); 'completion early 2028' (Jul 2026 notice) | QTS-143 p.1; QTS-163; QTS-138 |
| Hansen Rd link road (Frankton) | NZTA alliance | Due to open October 2026 | Within package | Oct 2026 (upcoming works page: opens Mon 12 Oct 2026) | QTS-141 p.4; NZTA upcoming works page |
| Pūāhuru walking & cycling bridge over SH6 (Jim's Way/Ferry Hill Dr–Hardware Lane) | NZTA (alliance build); Queenstown Trails; QLDC crossings | Early works (soil nailing) under way | $12.6m approved | Completion by end of 2027 | QTS-147; QTS-141 p.5; NZTA Pūāhuru page |
| (d) SH6A Frankton–Queenstown: 4 signalised intersections + 3 pedestrian signals | NZTA | Designed; not funded for construction | No robust cost estimate | — | QTS-113 p.2 |
| (e) Hawthorne Dr & Grant Rd signals; pedestrian signals near Hardware Lane | NZTA | Designed; not funded for construction | No robust cost estimate | — | QTS-113 p.2 |
| (f) Southern corridor: Humphrey St & Lucas Place roundabouts to signals; Ross St pedestrian signals | NZTA | Designed; not funded for construction | No robust cost estimate | — | QTS-113 p.2 |
| (g) SH6 Ladies Mile eastbound bus lane (Howards Dr–Shotover bridge) | NZTA | Designed; not funded for construction | No robust cost estimate | — | QTS-113 p.2 |
| QSNP T19: Frankton Flats Network Improvements | NZTA | Immediate programme development priority (not an investment recommendation) | Indicative $250m (can be staged) | QSNP Phase 1–2 | QTS-130 pp.58–59 |
| QSNP T19: Ladies Mile Corridor Improvements | NZTA | Investment case / pre-implementation | $0.75m–$1m (next stage) | Immediate | QTS-130 pp.58–59 |
| QSNP T19: Southern Corridor Early Interventions | NZTA | Next-stage development | $0.75m–$1m (next stage) | Immediate | QTS-130 pp.58–59 |
| QSNP T19: Arthurs Point Crossing (Edith Cavell Bridge replacement) | QLDC-led | In discussion NZTA–QLDC; 'funding to be considered in due course' | Indicative $60m–$80m (assumes 51% FAR) | Not stated | QTS-130 pp.58–59; QTS-138 |
| QSNP T19: Offline public transport investment case (incl. relationship with private sector proposals) | NZTA | Next-stage development | $1m–$2m (investment case) | Offline PT lines are QSNP Stage 3 (10–30 yrs) | QTS-130 pp.44, 51–52, 58–59 |
| QSNP T19: Time-of-use charging | NZTA | Next-stage development | $1m–$2m | Not stated | QTS-130 pp.54, 58–59 |
| QSNP T19: Alternative funding and financing | NZTA with partners | Workstream | No cost stated | Not stated | QTS-130 pp.56, 58–59 |
| QSNP: New Kawarau River crossing (road or offline PT) | NZTA | Long-term (Stage 3) | Cost band $$$$ ($250m–$999m) | 10–30 years | QTS-130 pp.44, 49–50; QTS-138 |
| SH6 Frankton Flats network improvements (RLTP entry) | NZTA | Listed in RLTP mid-term review | Property $5.3m (25/26) + $5.3m (26/27); implementation $32.7m (26/27), $98.1m 2024-30 | 2025/26–2029/30 | QTS-148 p.71 |
| Stanley St Corridor Improvements (Queenstown Town Centre DBC) | NZTA | Listed in RLTP; regional priority 11 | Pre-impl $1.308m; property $2.12m; implementation $35.098m (10-yr) | 10-yr RLTP | QTS-148 pp.71, 81 |
| SH6/6A Queenstown Offline High Capacity PT (implementation) | NZTA | Removed from SHIP 2024-34 (was ranked #2) | — | — | QTS-148 p.79 |
| Shepherds Hut Creek culvert, Queenstown | NZTA with QLDC | In NLTP 2024-27 | $2.176m | 2024-27 | QTS-098 pp.20, 79 |
| NZTA low cost/low risk PT infrastructure (RLTP NZTA line) | NZTA | In RLTP | $650k/yr; $1.95m 2024-27 | 2024-27 | QTS-148 p.79 |
Next steps as stated by NZTA
- Finish the Queenstown Package. Frankton intersection fully operational in the Phase 5 window, spring to winter 2028 (construction phases page). Howards Dr signals in place by summer 2027/28 [QTS-163]. Pūāhuru bridge complete by the end of 2027 [QTS-147].
- Turn the QSNP into fundable activity packages. Convert the strategic response "into fundable, consentable and deliverable activity packages" through RLTPs, State Highway Investment Proposals, NLTPs and business cases. "A critical next step is to agree the funding, financing, governance and delivery pathway for the programme." Initial development is to "focus on foundation and enabling activities" [QTS-130 p.58]. Table 19 items "don't constitute investment recommendations" [QTS-130 p.58].
- Progress the Table 19 immediate actions listed above [QTS-130 pp.58–59].
- Consider the QSNP for the 2027–30 NLTP [QTS-138]. The RLTP 2027–37 must be submitted to NZTA by the end of June 2027 [QTS-115].
- Keep discussing Edith Cavell Bridge replacement with QLDC, "with funding to be considered in due course" [QTS-138].
Last updated .
Sources
- QTS-164 Queenstown Package (project page)
- QTS-130 Queenstown Strategic Network Plan (August 2026)
- QTS-138 Strategic plan sets direction for Queenstown transport (Minister of Transport media release)
- QTS-226 OIA-23524 response: NZ Upgrade Programme Queenstown Package and Queenstown Strategic Network Plan
- QTS-219 Strategic Transport Plans – NZTA Board workshop paper (12 June 2026)
- QTS-218 Strategic Transport Planning – NZTA Board workshop pre-read pack (12 June 2026), Queenstown excerpt
- QTS-220 Strategic Transport Planning – NZTA Board workshop slides (June 2026)
- QTS-221 Queenstown Strategic Network Plan – optioneering approach and longlist (technical memo, final, 12 June 2026)
- QTS-222 NZTA Value, Outcomes & Scope Committee – minutes excerpt on the Queenstown Strategic Network Plan (9 July 2026)
- QTS-223 Queenstown Strategic Network Plan – NZTA Board paper for endorsement (12 August 2026)
- QTS-224 Queenstown Strategic Network Plan – summary (Attachment 1 to the August 2026 Board paper)
- QTS-225 NZTA Board minute excerpt – Queenstown Strategic Network Plan endorsed (12 August 2026)
- QTS-210 NZUP Queenstown Package – final business case cost estimates (spreadsheet)
- QTS-217 Queenstown Package – Benefits Realisation Plan (version 1, 21 August 2024)
- QTS-113 OIA-20263 response: Request made under the Official Information Act 1982 (NZUP Queenstown Package cost overrun)
- QTS-151 ORC Council Meeting 26 Aug 2026 – Agenda (incl. Q4 2025/26 performance & finance; Central Lakes sub-regional PT investment case)
- QTS-140 Queenstown Package 2025 project brochure
- QTS-141 Kā Huanui a Tāhuna – Huanui Pānui August 2026
- QTS-143 SH6 Ladies Mile – Howards Drive work notice, July 2026
- QTS-163 SH6 and Howards Drive intersection (project page)
- QTS-147 Green light for new SH6 walking and cycling bridge in Queenstown (media release)
- QTS-098 National Land Transport Programme 2024-27
- QTS-148 Mid-term review: Otago Southland Regional Land Transport Plan 2021-31
- QTS-139 Otago Central Lakes Deal – Final Deal Agreement and Schedule (signed)
- QTS-115 Otago and Southland Regional Transport Committees 23 February 2026 - Agenda