QTS-213 · Assessment and assurance · 2023

NZ Upgrade Programme (Queenstown) – Focused Scope Review report (final, 6 April 2023)

Two-page focused scope review dated 6 April 2023, following a cost workshop with the Kā Huanui a Tāhuna Alliance, the independent estimator Bond CM and NZTA. It finds the business case estimate, a P50 without escalation approved at $115m in November 2020, is no longer appropriate, noting escalation of about 22% from November 2020 to September 2022 and scope changes such as the move from a signalised roundabout to a fully signalised intersection. It identifies delay to designation, consenting, property and decisions as the main cost risk.

Key figures

  • Business case estimate $115m approved November 2020 (p.1)
  • Escalation about 22% Nov 2020 to Sept 2022 (p.1)
  • Project duration 36 months over three seasons (p.2)

Files

Actions recorded

No actions are recorded on this document.

Study cost

Not separately commissioned. This is an internal or corporate document.

Citation

NZTA (Waka Kotahi). NZ Upgrade Programme (Queenstown) – Focused Scope Review report (final, 6 April 2023) (2023). Released under OIA-23524.