QTS-212 · Board or committee paper · 2023
NZUP Queenstown – Appendix C: proposed prioritisation table (March 2023)
Options table attached to the 10 March 2023 NZUP Queenstown memo. It compares six scope options, from the full scope (Zones 1 to 6) down to Zone 3 only, with pros and cons for each. It states the Alliance estimate 'significantly exceeds the allocated baseline budget of $115m' and that the programme was forecast to run at least three years beyond its baseline. Some content is withheld under sections 9(2)(j) and 9(2)(g)(i).
Key figures
- Baseline budget $115m (p.1)
- Programme forecast to extend at least three years beyond baseline, to 2027 (p.1)
Files
- Open Main document (PDF, 392 KB) Opens in a new tab.
Main document
Actions recorded
No actions are recorded on this document.
Study cost
Not separately commissioned. This is an internal or corporate document.
Citation
NZTA (Waka Kotahi). NZUP Queenstown – Appendix C: proposed prioritisation table (March 2023) (2023). Released under OIA-23524.