QTS-092 · Board or committee paper · 2024
NZ Upgrade Programme: Queenstown Package way forward (OIA-20263, 30 January 2026)
Ministerial briefing BRI-2973 (1 February 2024), released under OIA-20263 on 30 January 2026 with the cost figures included. It is from Brett Gliddon, NZTA (Waka Kotahi) Group General Manager Transport Services, to Hon Simeon Brown (Transport) and Hon Nicola Willis (Finance). It seeks Joint Minister endorsement of the NZTA Board's 11 December 2023 decision to deliver a reduced scope NZUP Queenstown Package (SH6/6A intersection, Frankton bus hub, Howards Drive roundabout) at an estimated $250 million (P50, including a risk-adjusted contingency of $20 million). The package's allocation is $130 million; the additional $120 million would come from existing contingency within the $6.54 billion NZUP funding (principally the $116 million programme contingency), affecting choices for other NZUP projects. It explains costs by Queenstown constraints and the enlarged intersection. A decision was needed by mid-February 2024 for construction from March 2024 to 2028; delay would cost a year plus escalation and alliance costs of $900,000 per month. The Ministry of Transport supports the approach but notes uncertainty whether $250 million is P50 or P95, and that NZUP would have no contingency left. The remaining scope is described as a regional priority outside NZUP.
What the document says
Context and purpose: BRI-2973, 'NZ Upgrade Programme: Queenstown Package way forward', dated 1 February 2024 and signed by Brett Gliddon (pp1, 6), seeks endorsement from the Minister of Transport and Minister of Finance of the NZTA Board's 11 December 2023 decision to deliver a reduced scope Queenstown Package at an estimated $250 million (p2). The Ministry of Transport and Treasury were consulted (p2).
Context (pp2-3): Earlier briefings (BRI-2886, BRI-2919) advised the package was unaffordable within its $130 million allocation. From April 2023 NZTA progressed a reduced package (BP intersection, Frankton bus hub, Howards Drive roundabout), which NZTA assessed as the most critical elements and QLDC and ORC agreed were most important. The full scope also included SH6/6A bus priority, SH6 bus lanes and pedestrian improvements. Peak day population is projected to rise from 103,000 in 2021 to 204,000 in 2051, and the 2020 detailed business case estimated $670 million to $1.2 billion of economic losses over 40 years without investment (p3).
Cost (p3): The reduced package is $250 million, a P50 estimate including a risk-adjusted contingency of $20 million. It was independently reconciled and value engineered. Reasons given: short construction season, imported labour and materials, 36,000 vehicles per day with no viable detour, no lengthy night works, an enlarged intersection for bus priority, walking, cycling and bus hub facilities, and complex utility and stormwater works.
Funding (pp4-5): In August 2023 the Board received delegations to make scope decisions and reallocate funding between NZUP projects, but not to stop a project. NZUP funding for NZTA projects is $6.54 billion, including $116 million set aside as programme contingency, initially intended for the Queenstown and Canterbury Packages. The extra funding above $130 million would come principally from that contingency. Drury urban arterials, Rolleston and Brougham are said to remain affordable, with further advice after mid-2024 negotiations. The Board's 11 December 2023 approvals are listed in para 25.
Timing (p5): Detailed design is complete and consents are in place. A decision by mid-February 2024 would allow construction from March 2024 to 2028. Later decisions would delay completion by at least a year and add escalation and ongoing alliance and management costs of $900,000 per month.
Agency comments (p5): The Ministry of Transport supports the reduced scope as consistent with the August 2023 delegation. It notes uncertainty whether $250 million is P50 or P95, that it has not reviewed the Alliance contract, and that NZUP will be fully subscribed with no contingency for further escalation. Treasury did not have time to provide substantive comment.
Recommendations (p6): endorse the Board decision; note $120 million additional funding; note affordability within $6.54 billion from existing contingencies; note timing impacts; note public communication; and note most remaining scope is a regional priority outside NZUP. Ministerial signature blocks are blank in the release. Attachments: NZUP way-forward diagram (p7), location map with element prioritisation 1-7 (p8), and the updated SH6/SH6A intersection and bus hub layout (p9).
Mass rapid transit: The briefing says nothing about mass rapid transit. The deferred elements include the SH6A corridor improvements between Frankton and Queenstown (Attachment 2, priorities 4-5).
Key figures
- Reduced Package estimated cost $250 million (P50) (p3)
- Risk-adjusted contingency $20 million included in $250 million (p3)
- Current Queenstown allocation $130 million (p2, p4)
- Additional funding $120 million from wider NZUP (p6)
- NZUP funding available for NZTA projects $6.54 billion (p4)
- Peak day population 103,000 (2021) to 204,000 (2051) (p3)
- 2020 DBC: estimated economic losses $670 million to $1.2 billion over 40 years without investment (p3)
- 36,000 vehicles per day through SH6/6A (p3)
- Construction March 2024 to 2028 (p5)
- NZUP programme contingency $116 million, initially intended for Queenstown and Canterbury Packages (p4)
- Ongoing alliance and management costs $900,000 per month (p5)
- Attachment 1: NZUP total funding allocation $6.5B; P95 cost risk $8B+; projects in construction $2.3B+; significant projects in procurement $3.5B+ (cumulative $5.8B+); pre-implementation $0.7B+; paused $0.6B (p7)
Files
- Open Main document (PDF, 1.2 MB) Opens in a new tab.
Main document
Actions recorded
Joint Ministers to endorse the NZTA Board decision to complete the reduced scope Queenstown Package at an estimated cost of $250 million.
Not assessed · Central government / Ministers · By mid-February 2024
Endorse the decision by the NZTA Board to complete the reduced scope Queenstown Package
Joint Ministers to note that the reduced scope requires $120 million additional funding from the wider NZUP, drawn from existing contingencies within the $6.54 billion allocation.
Not assessed · Central government / Ministers
Note that progressing the reduced scope Queenstown Package will require additional funding of $120 million
Subject to endorsement, change the current alliance contract to deliver the reduced scope up to the $250 million funding limit.
Not assessed · NZTA · Construction from March 2024
Make changes to the current alliance contract
Communicate with the public about the updated project scope and cost once the decision is confirmed.
Not assessed · NZTA · Once decision confirmed
Provide a further briefing on affordability of the Canterbury Package and Drury urban arterials once other NZUP negotiations conclude.
Not assessed · NZTA · Mid-2024
We will provide you with a further briefing at that point
Treat most of the remaining Queenstown Package scope as a regional priority for transport investment outside NZUP; provide further advice to Joint Ministers.
Not assessed · NZTA
NZTA considers most of the remaining scope remains a regional priority
Study cost
Not separately commissioned. This is an internal or corporate document.
Citation
NZTA (Waka Kotahi). NZ Upgrade Programme: Queenstown Package way forward (2024). BRI-2973.