QTS-073 · Accountability report · 2022

2021 - 2022 Annual Report

QLDC's 2021/22 Annual Report, year one of the 2021-2031 Ten Year Plan, records capital expenditure of $160.4m, 'below estimate by $86.9M' (p.19). Queenstown Town Centre Arterials Stage 1 spent $26.4m with $4.08m deferred, Queenstown Street Upgrades (CIP) $32.6m with $2.61m deferred, and Whakatipu Public Transport had $1.36m deferred (p.30). Carry-forwards totalled $42.79m (p.30). Arterial construction began in September 2021 (p.5). No mass rapid transit reference was found.

What the document says

Context and purpose. Annual Report for the first year of the 2021-2031 Ten Year Plan.

Transport. 'Overall capital expenditure was $160.4M which is below estimate by $86.9M for the year ended 30 June 2022' (p.19). Queenstown Town Centre Arterials Stage 1 cost $26,424,670 at year end with $4,081,434 deferred; Queenstown Street Upgrades (Crown Infrastructure Partners) $32,594,049 with $2,613,435 deferred; and Whakatipu Public Transport $1,362,480 deferred (p.30). Carry-forwards totalled $42.79m, approved in September for 2022-23 and 2023-24 (p.30). Arterial construction began in September (p.5). The Mode Shift Plan is listed as a priority initiative (p.26), and 'limited public transport' is a Spatial Plan challenge (p.40).

Performance.

Mass rapid transit: No reference to mass rapid transit was found in the text read.

Key figures

  • Capital expenditure $160.4m, $86.9m below estimate (p.19)
  • Arterials Stage 1 $26,424,670 at year end; $4,081,434 deferred (p.30)
  • Street Upgrades (CIP) $32,594,049; $2,613,435 deferred (p.30)
  • Whakatipu Public Transport $1,362,480 deferred (p.30)
  • Carry-forwards $42.79m (p.30)

Files

Public copies

Actions recorded

  • Defer $4.08m of Arterial Stage 1 budget

    Not assessed · QLDC · 2022/23

    $4,081,434 deferred

  • Defer $2.61m of Queenstown Street Upgrades budget

    Not assessed · QLDC · 2022/23

    $2,613,435 deferred

  • Defer $1.36m of Whakatipu Public Transport budget

    Not assessed · QLDC · 2022/23-2023/24

    Whakatipu Public Transport: $1,362,480 deferred

  • Carry forward $42.79m of capital projects

    Not assessed · QLDC · 2022/23-2023/24

    Carry-forwards $42.79M

Study cost

Not separately commissioned. This is an internal or corporate document.

Citation

2021 - 2022 Annual Report (2022).