QTS-024 · Accountability report · 2019

2018/19 Annual Report (Rīpoata ā-tau)

QLDC's 2018/19 Annual Report, year one of the 2018-2028 Ten Year Plan, records capital expenditure 'below estimate by $28.7m' (p.7) and some $53m short of the original Ten Year Plan budget (p.10), citing 'delay in the NZTA approval process for major transport improvements in Queenstown'. Carry-forwards of $47.1m were approved (p.13). Town Centre pedestrianisation spent $1.13m of a $2.50m budget (p.7). A capital works KPI of 52% missed the >80% target (p.54). The Wakatipu Way to Go partnership (QLDC, ORC, NZTA) launched in January 2019 (p.3). No mass rapid transit reference was found.

What the document says

Context and purpose. The first Annual Report under the 2018-2028 Ten Year Plan, signed 10 October 2019 (p.23).

Transport. Capital expenditure was 'below estimate by $28.7m for the year ended 30 June 2019' (p.7) and 'some $53m short of the original 2018 Ten Year Plan budget' (p.10), attributed to 'delay in the NZTA approval process for major transport improvements in Queenstown' (p.10). Carry-forward projects totalling $47.1m were approved in August 2019 (p.13). Queenstown Town Centre pedestrianisation spent $1.13m against $2.50m, being 'dependent on NZTA funding' and scheduled for 2019-2026 (p.7). Year-end costs for the Town Centre Arterials were $632,818 and Queenstown Parking Improvements $910,111 (p.13). The water taxi/ferry network cost $3,168,172 (p.12). The Wakatipu Way to Go partnership of QLDC, ORC and NZTA, launched January 2019, aims for 'an enduring, affordable, safe transport system with a range of choices' (p.3).

Performance. The capital works KPI was 52% against a target above 80%, not met, attributed to deferred budgets and dependence on developer agreements, joint ventures and 'NZTA funding approvals' (p.54). Roading requests resolved on time: 78% (p.54).

Mass rapid transit: No reference to mass rapid transit was found in the text read.

Key figures

  • Capital expenditure $28.7m below estimate (p.7); ~$53m short of Ten Year Plan (p.10)
  • Carry-forwards $47.1m (p.13)
  • Capital works KPI 52% vs >80% target (p.54)
  • QTC pedestrianisation $1.13m vs $2.50m budget (p.7)
  • Town Centre Arterials $632,818; Parking Improvements $910,111 at year end (p.13)

Files

Public copies

Actions recorded

  • Carry forward $47.1m of capital projects to 2019/20, including town centre arterial, pedestrianisation and parking work

    Not assessed · QLDC · 2019/20

    Carry-forward projects totalling $47.1m

  • Deliver Queenstown Town Centre pedestrianisation, dependent on NZTA funding

    Not assessed · QLDC · 2019-2026

  • Deliver the Wakatipu Way to Go transport programme

    Not assessed · Way to Go · From January 2019

    partnership between QLDC, Otago Regional Council and NZTA

Study cost

Not separately commissioned. This is an internal or corporate document.