QTS-019 · Statutory plan · 2019

Annual Plan 1 July 2019 - 30 June 2020

QLDC's Annual Plan for 2019/20, adopted 27 June 2019, updates year two of the 2018-2028 Ten Year Plan. Total capital expenditure is $163.4m, about $14m (7.8%) below the Ten Year Plan, 'due primarily to the time required to work through NZTA process for some transport-related projects', naming the Town Centre Masterplan arterial roads and parking buildings (p.13). Transport capital is $59.37m against $76.20m in the Ten Year Plan, a $16.83m reduction; parking facilities fall from $11.97m to $1.60m, noted as 'Deferral of capex for Queenstown parking' (p.31). No mass rapid transit reference was found.

What the document says

Context and purpose. The 2019/20 Annual Plan sets the budget for the second year of the 2018-2028 Ten Year Plan and explains variances from it. It was adopted on 27 June 2019 (p.15).

Transport. The plan reports total 2019/20 capital expenditure of $163.4m, about $14m (7.8%) below the Ten Year Plan, 'due primarily to the time required to work through NZTA process for some transport-related projects', citing the Queenstown Town Centre Masterplan arterial roads and parking buildings (p.13). In the funding impact tables, transport capital is $59.37m against $76.20m in the Ten Year Plan, a variance of $(16.83)m, and parking facilities capital is $1.60m against $11.97m, a variance of $(10.37)m with the note 'Deferral of capex for Queenstown parking' (p.31). A transport improvement fund holds 'Funds set aside to subsidise public transport and the development of public transport infrastructure' (p.36). Active travel and park-and-ride are not mentioned in the portion read.

Correction to background. On the live document, the $16.83m reduction is 22.1% of the Ten Year Plan figure (28.3% is relative to the Annual Plan figure), and $163.4m is the district's total capital expenditure for the year.

Mass rapid transit: No reference to mass rapid transit was found in the pages read (to p.45).

Key figures

  • Total capital expenditure 2019/20 $163.4m, about $14m (7.8%) below the Ten Year Plan (p.13)
  • Transport capital $59.37m vs $76.20m Ten Year Plan, variance $(16.83)m (p.31)
  • Parking facilities capital $1.60m vs $11.97m, variance $(10.37)m, 'Deferral of capex for Queenstown parking' (p.31)

Files

Public copies

Actions recorded

  • Reduce 2019/20 transport capital to $59.37m (from $76.20m) while NZTA processes for major transport projects are worked through

    Not assessed · QLDC · 2019/20

    time required to work through NZTA process

  • Defer Queenstown parking capital: parking facilities $1.60m (from $11.97m)

    Not assessed · QLDC · 2019/20

    Deferral of capex for Queenstown parking

  • Progress Town Centre Masterplan arterial roads and parking buildings through the NZTA process

    Not assessed · NZTA · 2019/20

    Queenstown Town Centre Masterplan arterial roads and parking buildings

Study cost

Not separately commissioned. This is an internal or corporate document.

Citation

Annual Plan 1 July 2019 - 30 June 2020 (2019).