Investment and Delivery Committee Paper: Queenstown Transport Programme Procurement
Waka Kotahi NZ Transport Agency paper to the Investment and Delivery Committee (meeting 17 September 2020) seeking approval of the Queenstown Transport Programme Procurement Strategy and Plan. The Programme combines two Crown Infrastructure Partners-funded shovel-ready projects (Queenstown Town Centre Street Upgrades and Arterials Stage 1), NZ Upgrade Programme (NZUP) public transport and walking and cycling upgrades on SH6 and SH6A, and Wakatipu Active Travel Network Stage 1, valued at circa $230M. After comparing traditional, panel and collaborative models, and competitive, hybrid and pure alliances, it recommends a Pure Alliance procured jointly with Queenstown Lakes District Council (QLDC), with a Memorandum of Understanding between the client partners. Reasons include coordinated delivery to limit disruption, broader outcomes and economic stimulus during COVID-19 suppressed demand. Projects would sit under individual Target Outturn Costs. Future projects (later Active Travel stages, Lakeview, Public Transport Interchange) could be allocated on a 'yours to lose' basis. Attachment 1 shows the NZUP element with a cost cap of $90M.
What the document says
Context and purpose: This Investment and Delivery Committee paper (dated 9 September 2020; meeting 17 September 2020; final version) asks the Committee to recommend that the Waka Kotahi Board approve the Queenstown Transport Programme Procurement Strategy and Plan, using a Pure Alliance procured jointly with QLDC (p1). ELT sponsors are Brett Gliddon and Matthew Walker; it was prepared by Kesh Keshaboina and legally reviewed by Lucy Riddiford (p1).
Programme: The Programme comprises the Crown Infrastructure Partners (CIP) funded Queenstown Town Centre Street Upgrades and Arterials Stage 1 (balance funded by QLDC), NZUP-funded public transport and walking and cycling upgrades on SH6 and SH6A, and Wakatipu Active Travel Network Stage 1 funded through the NLTP, to be delivered over four years (p2). Its scale is put at circa $230M (p1). Attachment 1 (p7, image) gives indicative caps: Town Centre Street Upgrades ($60M, CIP cap $35M), Arterials Stage 1 ($65M, CIP cap $50M; PT hub potential inclusion unfunded $27M), Active Travel Stage 1 ($16M) and Stage 2 ($23M funding application), and NZUP ($90M, NZUP cap $90M, completion 2024, then in business case phase).
Options: Traditional, panel (QLDC three waters panel) and collaborative (Alliance) models were ranked, with the Alliance first (p3). Competitive, hybrid and pure alliances were then compared; competitive and hybrid were judged to lack time given CIP and NZUP deadlines, so a Pure Alliance was preferred (p4). Expected efficiencies include single programme governance, consistent design and construction, coordinated resources, early works packages and a more attractive market proposition (p4). The Alliance scope would cover design and construction; business case, property and consenting would sit outside it (p4).
Market: The local horizontal infrastructure market was mainly projects under $10m; QLDC's three waters programme runs at about $70m a year; NZUP contains $6.8Bn of transport projects ($5.4Bn roading) (p5). Risks are the accelerated procurement timeframe, client partner alignment and commercial complexity with multiple funding sources (pp5-6). Individual Target Outturn Costs (TOCs) are recommended for each project, and further projects may be allocated on a 'yours to lose' basis (p6).
Mass rapid transit: The paper says nothing about mass rapid transit. It mentions a future Public Transport Interchange as a possible Alliance project (p6).
Key figures
- Programme circa $230M (p1)
- NZUP element indicative cost $90M, NZUP cap $90M (Attachment 1, p7)
- Town Centre Street Upgrades $60M, CIP cap $35M (p7)
- Arterials Stage 1 $65M, CIP cap $50M; PT hub potential inclusion unfunded $27M (p7)
- Active Travel Stage 1 $16M; Stage 2 funding application $23M (p7)
- NZ Upgrade Programme $6.8Bn of transport projects ($5.4Bn roading) (p5)
- QLDC 3 Waters programme in the order of $70m per annum (p5)
Files
- Open Main document (PDF, 1.1 MB) Opens in a new tab.
Main document
Actions recorded
Board to approve the Queenstown Transport Programme Procurement Strategy and Plan.
Not assessed · NZTA · Meeting 17 September 2020
Approves the Queenstown Transport Programme Procurement Strategy and Plan
Board to approve a Pure Alliance delivery model procured jointly with Queenstown Lakes District Council.
Not assessed · NZTA · Meeting 17 September 2020
Approves the use of a Pure Alliance delivery model procured jointly with Queenstown Lakes District Council
Board to note that Waka Kotahi and QLDC will enter a Memorandum of Understanding setting the basis for the partnership, including commercial principles.
Not assessed · NZTA
Notes that a Memorandum of Understanding will be entered into
Establish projects within the Programme under individual Target Outturn Costs (TOCs).
Not assessed · NZTA
projects within the Programme be established under individual Target Outturn Costs
Allow additional future projects (later Active Travel stages, Lakeview, Public Transport Interchange) to be allocated to the Alliance on a 'yours to lose' basis.
Not assessed · NZTA
may be allocated to the Alliance on a strictly 'yours to lose' basis
Study cost