QTS-100 · Accountability report · 2024
Attachment B: Finance YTD CAPEX Project Report - July to December 2024
QLDC's year-to-date capital project report for July-December 2024 shows total capital of $60.7m against a $70.0m year-to-date budget (87%), a $152.5m full-year adjusted budget and a $144.3m forecast. Transport lines include arterial Stage 1 within the Crown Infrastructure Partners programme ('opening scheduled for 30 January 2025'), Public Transport Assets - Whakatipu 'placed on hold pending decision on local share allocation of transport budgets', Arthurs Point to CBD active travel close-out, Wānaka Pool to School active travel, Stanley Street site works and temporary parking (final sealing October 2025) and $100k unsubsidised to update the Arthurs Point Bridge business case. No mass rapid transit reference.
What the document says
Context and purpose. This is Attachment B (item 2b) to QLDC's December 2024 finance reporting, listing each capital project's year-to-date actual, budget and forecast with commentary (pp.79-83 of the agenda).
Totals. Year-to-date actual $60,666,969 against a $69,994,394 budget (87%); full-year adjusted budget $152,509,508 and forecast $144,349,894, $8.16m below.
Transport lines. Within the Crown Infrastructure Partners programme (combined YTD $20.0m against $21.5m; full-year $32.3m), arterial Stage 1 is reported 'with opening scheduled for 30 January 2025', and Queenstown Street Upgrades ($657k YTD, $2.4m full-year) note a snag programme resuming in March 2025. In the PMO transport group, Public Transport Assets - Whakatipu is 'placed on hold pending decision on local share allocation of transport budgets'; Arthurs Point to CBD Active Travel ($366k YTD, $847k full-year) is closing out with 100% Transport Choices funding; Wānaka Pool to School active travel ($651k YTD, $1.4m) is due for completion by June 2025; the minor improvements programme ($3.3m full-year) includes $1.2m subsidised for Ballantyne Road. Stanley Street site works and temporary parking ($28k YTD, $1.1m) has final sealing deferred to October 2025. Arthurs Point Bridge Crossing carries '$100k unsub budget to update business case'. Resilience works on the Crown Range and Bennetts Bluff have 75% NZTA funding with procurement imminent. Transport renewals total $11.3m full-year.
Background. the live report shows the line within a combined PMO transport row ($1.21m full-year) with the 'local share allocation' wording above.
Mass rapid transit: None. The only public transport item is the Public Transport Assets - Whakatipu line.
Key figures
- YTD capital $60,666,969 vs $69,994,394 budget (87%)
- Full-year adjusted budget $152,509,508; forecast $144,349,894
- CIP programme (arterial Stage 1 and street upgrades) YTD $20.0m; full-year $32.3m
- Arthurs Point to CBD active travel full-year $847k; Stanley St site works $1.1m
Files
- Open Main document (PDF, 1.1 MB) Opens in a new tab.
Main document
- Open Part 2 (PDF, 1.4 MB) Opens in a new tab.
Part 2
- Open Part 3 (PDF, 1.3 MB) Opens in a new tab.
Part 3
Public copies
- 2b-attachment-b-finance-ytd-capex-project-report-july-to-december-2024.pdfsportrec.qldc.govt.nz (leaves this site) (opens in new tab)
- 2a-attachment-a-december-2024-finance-management-report.pdfsportrec.qldc.govt.nz (leaves this site) (opens in new tab)
- 2-december-2024-ytd-financial-overview-paper.pdfwww.qldc.govt.nz (leaves this site) (opens in new tab)
Actions recorded
Open arterial Stage 1
Not assessed · 30 January 2025
with opening scheduled for 30 January 2025
Hold Public Transport Assets - Whakatipu pending a decision on local share allocation of transport budgets
Not assessed · QLDC · Pending decision
placed on hold pending decision on local share allocation of transport budgets
Complete Stanley Street site works and temporary parking final sealing
Not assessed · QLDC · October 2025
Final sealing construction works now to be completed Oct 2025
Update the Arthurs Point Bridge crossing business case ($100k unsubsidised)
Not assessed · QLDC · 2024/25
$100k unsub budget to update business case
Complete Wānaka Pool to School active travel
Not assessed · QLDC · June 2025
Project completion anticipated by Jun 25
Procure Crown Range and Bennetts Bluff resilience works (75% NZTA funded)
Not assessed · QLDC · 2024/25
Procurement imminent
Study cost
Not separately commissioned. This is an internal or corporate document.
Citation
Attachment B: Finance YTD CAPEX Project Report - July to December 2024 (2024).